Introduction:
Grede Vassar is a high production shop, specializing in small iron castings. Their facility can produce 112 tons of castings per day. They utilize the shell sand technology for their casting production.
General Foundry Information
Product Line:
Casting Metal Type:
Melting Facilities:
Sand Facilities:
Cleaning Facilities:
Heat Treating:
Pattern Shop:
Other:
Project Objective:
The objective and need of the foundry was to get better control over their shell sand coating operation. The process was highly labor intensive and had minimal process control. The sand coating operation provides the foundry with 100% of their sand. They also sell some shell coated sand to other foundries. Along with getting control over the coating operation, they also wanted to increase the flexibility and product repeatability. For information the original system was installed in the mid 1960’s.
Original Problems:
Solution:
They installed the MT Systems REALTIME Computerized Resin Control System during February 1989. The basis of the system was to give them the flexibility to produce any type of coated sand by selecting the desired recipe (No manual adjustments). The system was to accomplish this by using modern process control techniques and then fully document the batch data.
To accomplish the above goals, the mullor was outfitted with the following hardware:
Their production works as follows:
The operator initiates the days production by turning the heating drum controls on, entering which recipe he needs to produce, then turning the control over to automatic mode. Once in automatic mode, the computer will produce continuous batches until the recipe is changed, the system is switched to manual mode, or a problem occurs. All batches are mixed from a recipe. A recipe is a set of instructions that includes steps and ingredients used in the making of a batch of sand.
First the system weighs up the sand to its setpoint. The system then takes the actual sand weight and calculated the other ingredients setpoints. Next, the sand is discharged into the heating drum. While the sand is in the heating drum the other ingredients are being weighed up, the sand is discharged into the mullor. At precisely the right time the other ingredients are charged in the prescribed manner outlined by the recipe. After the mix cycle is complete the coated sand is discharged to the delivery system.
The system provides complete documentation for managements review. The system produces daily operations log and a consumption report. The daily operations log documents what went into each batch of sand. This consists of the recipe; mix time, batch finish time, sand weight, ingredient weights, sand temperature and ambient conditions. The consumption report documents total sand and ingredients consumed, total mixer run time, total bat h produced. This data is categorized by shift, and then broken down into a daily, month-to-date, and year-to-date format. All data is permanently stored for future recall.
It is also important to note that if the process variables deviate from setpoint the system does alarm and shuts the operation down. The computer also provides diagnostics that indicates which variable or discrete input is shutting the process down.
Results and Benefits:
Monetary Savings/Pay Back:
Other:
The project engineer responsible for the project feels very strongly about the system and how it has streamlined their operation. He knows that they are producing the highest quality sand they’ve ever produced. He is committed to this type of process control and wants to implement it in other areas of the plant.
The operators are also very pleased with the system. They played an integral parting the design of the system, because they were the only ones who could make the old system work and they thoroughly understood the process.